Shed Spare Room — Build Implementation Plan

For the builder (you): This plan is written task-by-task. Each task lists materials, tools, exact steps, and a verification checkpoint. Tick boxes as you complete them. Take a photo after each verification — this is your "commit." If a step doesn't make sense or seems wrong when you're standing in the shed with the tool in your hand, stop and ask rather than guessing.

Goal: Build a 6700 × 3780 mm insulated, lined, finished spare room inside the existing shed at Mittagong, suitable for use as a home office, guest bedroom, and chill space.

Approach: Hybrid room-in-a-room — three new freestanding stud walls (front, left, right) plus one shared back wall reusing the shed's existing wall and windows. Raised insulated timber subfloor with vinyl plank. New insulated flat ceiling at 2370 mm AFL. Owner-built carpentry, licensed electrician for all wiring, Scandinavian warm-modern aesthetic.

Reference spec: docs/superpowers/specs/2026-04-07-shed-spare-room-design.md — read this before starting any phase.

Total budget: ~$14,100 AUD (construction $9,600 + furniture $4,500)

Estimated owner labour: 60–90 hours, spread over 4–8 weekends depending on pace.


Build Phase Overview (the big picture)

Phase What happens Owner labour Sparky needed?
0 Prep + measurement + materials shopping 6–8 h No
1 Site prep, slab clean, set out 3–4 h No
2 Subfloor: bearers, batts, ply 8–10 h No
3 Wall framing: bottom plates, studs, top plates 10–12 h No
4 Back wall battens + ceiling joists 6–8 h No
5 Door & window opening prep 2–3 h No
6 Sparky rough-in 1 h owner + sparky day YES
7 Insulation: walls, back wall, ceiling 6–8 h No
8 Vapour control layer (critical detail work) 4–6 h No
9 Plasterboard hanging 8–10 h No
10 Plasterboard set + sand (3 coats) 8–12 h spread over a week No
11 Sparky fit-off 0.5 h owner + sparky half-day YES
12 Painting 6–8 h No
13 Vinyl plank flooring + skirtings 8–10 h No
14 Door hanging + trim 3–4 h No
15 Window blinds, vent, air sealing 2–3 h No
16 Furnishing + final touches 4–6 h No

Phase 0: Preparation, Measurement, and Procurement

Goal: Know exactly what you're building, in exactly what space, with exactly which materials on hand before you swing a hammer.

Task 0.1: Verify the shed measurements

Task 0.2: Confirm shed structure for fixings

Task 0.3: Source the licensed electrician

Task 0.4: Materials list — generate the BOM

This is the master list. Order in 3 batches: framing+floor, lining+insulation, finishes+fittings. Each batch has its own task below.

Task 0.5: Bill of Materials — Phase 1 (Framing + Subfloor)

Order this batch first. Take delivery before Phase 2 starts.

Timber (all MGP10 pine unless noted):

Item Qty Spec Approx cost
90 × 35 mm pine stud 35 lengths × 2.4 m wall studs $200
90 × 45 mm pine 12 lengths × 2.7 m top + bottom plates, top plate doubled $130
190 × 45 mm pine 15 lengths × 3.9 m ceiling joists (span short axis) $350
70 × 45 mm pine 16 lengths × 3.9 m subfloor bearers/joists $160
190 × 45 mm galv joist hangers 15 ceiling joist hangers $75
75 × 75 mm galv angle brackets 8 subfloor lateral restraint to slab $30
50 × 35 mm pine batten 12 lengths × 2.4 m back wall battens $50
15 mm structural plywood 8 sheets × 2400 × 1200 subfloor $600
90 × 19 mm pine 6 lengths × 2.4 m door jamb framing, noggins $50

Fixings:

Item Qty Spec Approx cost
Hilti / Ramset DX nails or similar 1 box (50) for angle brackets to slab $40
Construction adhesive 4 tubes Liquid Nails Heavy Duty or similar $30
Bugle head screws 75 mm 1 box (200) stud framing $25
Bugle head screws 50 mm 1 box (500) ply to joists $25
Self-drilling Tek screws 14g × 25 mm 1 box (100) back-wall battens to shed steel $20
100 × 4 mm bugle screws 1 box (50) top plate joins $15

Subfloor protection:

Item Qty Spec Approx cost
200 µm builder's plastic 1 roll × 4 m × 50 m DPM under joists $80
Closed-cell foam pad strip 1 roll × 50 mm × 6 mm × 30 m DPC pad under joist contact points $25
Cloth duct tape 2 rolls sealing DPM joins $15

Subtotal Phase 1: ~$1,990

Task 0.6: Tools required — verify you have or can borrow

Tool Required for Have?
Cordless drill + driver Everything
Circular saw or mitre saw Cutting timber to length
Cordless impact driver Driving Tek screws into steel
Hammer drill (corded or strong cordless) Drilling slab for bottom plate fixings
2.4 m straight edge or laser level Levelling joists, plumbing walls
600 mm and 1200 mm spirit levels Plumb and level checks
8 m tape measure Setting out
Carpenter's square Marking cuts
Chalk line Setting out walls on slab
Stanley knife + blades Cutting plasterboard, batts, vinyl
Hand saw Trim cuts
Ladder or trestle (1.8 m) Ceiling work
Stud finder Locating shed structure
Safety: glasses, ear protection, gloves, dust mask, knee pads Always
Work lights (LED on stand) Shed is dark inside the build zone

Task 0.7: Communicate with household

Phase 0 verification: Measurements logged, sparky walkthrough booked, materials ordered, tools confirmed, household briefed. Take a "before" photo of the shed build zone — empty slab, looking from the front wall location toward the back windows.


Phase 1: Site Prep & Set-Out

Goal: Empty, clean slab with the room outline marked in chalk so you can see exactly where every wall is going.

Task 1.1: Clear the build zone

Task 1.2: Establish reference lines

Task 1.3: Mark wall plate centrelines

Phase 1 verification: All four wall lines snapped, square confirmed, stud positions marked, door opening marked. Photo of the chalk-marked slab from above (stand on a ladder).


Phase 2: Subfloor (Bearers, Batts, Ply)

Goal: A flat, insulated, level timber floor over the slab, ready to receive vinyl plank later.

Task 2.1: Patch the slab

Task 2.2: Install damp-proof membrane

Task 2.3: Lay the bearers/joists

The joists run across the short axis (3780 mm direction), spaced at 450 mm centres along the 6700 mm long axis. 70 × 45 on edge gives a 70 mm tall cavity for batts. You need 16 joists (6700 / 450 = ~15 spaces + 1).

Task 2.4: Insulate between the joists

Task 2.5: Lay the ply subfloor

Task 2.6: Protect the deck

Phase 2 verification: Subfloor is complete, level, insulated, protected. Photo from each corner.


Phase 3: Wall Framing

Goal: Three new freestanding stud walls (front, left, right) framed and standing, plumb and square.

Task 3.1: Cut the bottom plates

Task 3.2: Cut and mark the top plates

Task 3.3: Cut the studs

Important sequencing note: Final stud length depends on knowing the exact height from subfloor to the underside of the ceiling joists, which aren't installed until Phase 4. However, the ceiling joists sit on top of the wall top plates, so the stud length is actually independent of joist depth — it's determined by desired ceiling height minus top plate (90 mm) minus bottom plate (90 mm). Target: 2370 mm ceiling AFL − 90 mm bottom plate − 90 mm top plate = 2190 mm stud length. Verify this calculation in the shed: measure from the ply subfloor to the height where you want the underside of the ceiling joists (2370 mm), subtract 180 mm for the two plates.

Task 3.4: Frame walls flat on the subfloor

You'll build each wall as a complete assembly (bottom plate + studs + top plate + noggins) flat on the deck, then stand it up and fix it in place. This is standard platform framing.

Task 3.5: Tie the walls together at the corners

Task 3.6: Add the second top plate

Phase 3 verification: Three walls framed, plumb, square, tied together at corners with double top plate. Door opening framed correctly. Photo from each corner of the room interior.


Phase 4: Back Wall Battens & Ceiling Joists

Goal: Battens fixed to the existing shed back wall ready for insulation and lining; new ceiling joists installed at 2370 mm finished height.

Task 4.1: Install back-wall battens

Condensation risk: The shed's metal back wall will be the cold surface where moisture condenses. The vapour control layer (Phase 8) is the primary defence, but any VCL failure traps moisture with no drying path. To mitigate this, leave a small ventilated air gap at the top and bottom of the batten cavity so any moisture that does get through can dry by convection into the shed roof space.

Task 4.2: Frame the ceiling joists

The ceiling joists span the short axis (3780 mm, front wall to back wall) using 190 × 45 mm timber on edge. This gives a safe span with no mid-span support needed, and the 190 mm cavity depth properly accommodates R4.0 ceiling insulation without compression.

Task 4.3: Add ceiling joist noggins and fan blocking

Task 4.4: Confirm shed roof clearance and ceiling cavity ventilation

Summer heat: The air space between your new ceiling and the shed's metal roof will get extremely hot in summer. Without ventilation, this trapped air radiates heat down through the ceiling and degrades insulation performance.

Phase 4 verification: Back wall battened with ventilated cavity, ceiling joists installed at correct span and depth, fan blocking in place, roof space ventilation assessed. Photo of complete frame from inside the room.


Phase 5: Door & Window Opening Prep

Task 5.1: Confirm door opening

Task 5.2: Prepare window reveals

The existing shed windows need timber reveals (jamb extensions) to bring the window frame flush with the new interior wall surface (back wall battens + plasterboard total ~75 mm out from the shed wall).

Phase 5 verification: Door opening square and dimensioned, reveal timber cut and ready.


Phase 6: Sparky Rough-In

Goal: Cable, back boxes, ceiling fittings, smoke alarm cable all in walls and ceiling, certified by sparky.

Task 6.1: Walk through with sparky

Task 6.2: Add additional blocking for fittings

Phase 6 verification: Sparky has signed off rough-in inspection, cables tagged at sub-board, all boxes labelled. Owner has documented (photographed) every back box position and blocking position with a tape measure visible in the photo for future reference.


Phase 7: Insulation

Goal: All insulation in place with no gaps, ready for vapour layer.

Task 7.1: Side and front wall batts

Task 7.2: Back wall batts

Task 7.3: Ceiling batts

Phase 7 verification: Every wall and ceiling cavity insulated, no gaps, no compression, no batts crushed by cables. Photo of each wall and the ceiling.


Phase 8: Vapour Control Layer (Critical)

Goal: A continuous, taped, sealed plastic membrane on the warm-in-winter (interior) side of all walls and ceiling, preventing interior moisture from reaching the cold metal shed back wall and the cool insulation core.

This is the single most important quality detail in the build. Take your time.

Task 8.1: Materials

Task 8.2: Install vapour layer on walls

Task 8.3: Install vapour layer on the back wall (most important)

Task 8.4: Install vapour layer on the ceiling

Task 8.5: Inspection


Phase 9: Plasterboard Hanging

Goal: Walls and ceiling clad in 10 mm plasterboard, ready for setting.

Task 9.1: Materials

Task 9.2: Hang the ceiling first

Always do the ceiling first so wall sheets can support its edges.

Task 9.3: Hang the walls

Task 9.4: Install window reveals

Task 9.5: Install corner beads

Phase 9 verification: All ceiling and wall surfaces clad. No exposed insulation. All corners beaded. Photo of each wall and the ceiling.


Phase 10: Plasterboard Set & Sand

Goal: Smooth, paint-ready walls and ceiling.

Task 10.1: Materials

Task 10.2: First coat — tape and bed

Task 10.3: Second coat

Task 10.4: Third coat

Task 10.5: Final sand

Phase 10 verification: Walls and ceiling smooth, dust-free, ready for paint. Photo.


Phase 11: Sparky Fit-Off

Task 11.1: Sparky returns

Phase 11 verification: Every fitting installed and working, smoke alarm tested, certificate received.


Phase 12: Painting

Task 12.1: Materials

Task 12.2: Prep

Task 12.3: Undercoat

Task 12.4: Ceiling, 2 coats

Task 12.5: Walls, 2 coats

Phase 12 verification: Painted, dry. Photo.


Phase 13: Vinyl Plank Flooring & Skirtings

Task 13.1: Materials

Task 13.2: Install vinyl plank

Task 13.3: Install skirtings

Phase 13 verification: Flooring and skirting complete. Photo.


Phase 14: Door Hanging & Trim

Task 14.1: Hang the door

Task 14.2: Install door handle

Task 14.3: Architrave

Phase 14 verification: Door installed, swings cleanly, latches, looks finished.


Phase 15: Window Blinds, Vent, Air Sealing

Task 15.1: Roller blinds

Task 15.2: Ventilation (critical for a bedroom)

A sealed, insulated room used for sleeping needs adequate fresh air supply. A single 100 mm passive vent to the shed interior is not sufficient on its own — it provides no fresh air when the shed is closed up.

Task 15.3: Air sealing kit

Phase 15 verification: Window treatments installed, ventilation tested (cross-ventilation confirmed or mechanical extract fan installed), air sealing complete.


Phase 16: Furnishing & Final Touches

Task 16.1: Move furniture in

Task 16.2: Plug in heating and lighting

Task 16.3: Final cleanup

Task 16.4: Take "after" photos


Final Verification

Project complete. Move in. Sleep. Work. Hang out. Send photos.


Notes for the Builder

On pace: Don't try to rush this. The framing phase (3) can be done in a long weekend. Insulation + vapour layer (7-8) is a long weekend. Plasterboard (9-10) is the bottleneck — the setting compound needs 24 hours between coats, so it spans a week minimum. Plan accordingly.

On asking for help: Plasterboard hanging is much easier with two people. Ceiling sheets are basically impossible solo. Recruit a friend or hire a labourer for a day for the hanging phase only.

On variance from plan: If reality differs from spec — measurements wrong, materials unavailable, door doesn't fit — stop, photograph, and ask before improvising. Improvising in framing is fine; improvising in vapour control is dangerous.

On the "off the books" choice: Two things you must do regardless of compliance status: (1) licensed sparky for all wiring (legal requirement, insurance protection), (2) functioning smoke alarm. Everything else is your call.